Competitive bidding is designed to allow for bidders to compete,
consistent with the standards of quality and the terms and conditions
provided by the contract documents. This form may be open to all
interested parties or to just an invited group of contractors.
Generally, it involves a complete set of design and bidding documents
whereby award can be made on an objective (often to the low bidder)
basis.
On public work, Section 103, General Municipal Law, sometimes termed
the "low responsible bidder law," governs for material
purchases valued at greater than $10,000 and public work project valued
at over $20,000. Its highlights include the following:
- Requires a complete set of plans and specifications whereby
bidders compete on a level playing field
- Requires public advertisement with special note about school work
(…more)
- Requires award to the lowest responsive and responsible bidder (…more)
- Prohibits prequalification (including sublisting) and arbitrary
qualification prerequisites (…more)
- Requires free and open competition among equivalent materials,
products and manufacturers (…more)
- Prohibits breaking work into smaller packages to avoid the
threshold
- Prohibits post-bid negotiations of price and scope
- Requires a non-collusive bidding certificate to be submitted with
the bid.
PUBLIC ADVERTISEMENT: Section
102 of General Municipal Law requires advertisement of the project in
the official newspaper or newspapers of the public entity. The
advertisement must state the date, time and location for the public
opening of the bids. Pursuant to law, such advertisement is required at
least five days prior to bid opening. To be sure, that would be a
minimum based upon purchase contracts. For purposes of maximizing
competition on public work, a time frame of around four weeks is more
appropriate.
Special Note on Schools: It should be noted that Section 408 of
Education Law requires approval by the Commissioner of Education for the
State of New York prior to the advertisement for a public work project.
It is strongly recommended that attempts to circumvent the spirit of
this law by putting the documents on the street and then providing for
the legal minimum (five-day) advertisement later be shunned. Most
bidders will pay little attention to the documents until the firm bid
date is announced by the formal advertisement. The action, therefore,
will gain you little except, perhaps, the perception that some bidders
are being given an unfair advantage with back-door information.
AWARD TO THE LOW RESPONSIBLE
AND RESPONSIVE BIDDER: Of great importance to the public client as
well as to the contractor is the method of award clause, which makes
clear how bids will be treated after receipt. Section 103, General
Municipal Law, and other parallel sections of the State’s competitive
bidding statutes, require award to the lowest responsible bidder who has
submitted a responsive bid.
Essentially, there are only two valid reasons for rejecting a bid:
the bid is not responsive or not in compliance with the bidding
requirements or the bidder is not a responsible bidder.
Responsive Bids: A bid must be rejected if the non-compliance
with the bidding requirements is material or substantial. A material or
substantial variance with the bidding requirements is one that would
give the low bidder an unfair competitive advantage over the other
bidders or would hurt the interests of the public owner. Bids that are
qualified should not even be read and, if read, must be rejected as
non-responsive. Technical non-compliance or deviations that are minor or
not substantial, on the other hand, may be waived if it is in the best
interest of the owner to do so.
Responsible Bidders: The public owner has not only the absolute
right to determine, post-bid, whether a low bidder is
"responsible" but also the duty to make such a determination.
Although the making of such a determination may be burdensome, it is to
the great advantage of the public client to undertake the necessary
investigations of a bidder’s prior performance, its financial and
technical capacity to undertake the project at hand and its reputation
in the marketplace. Given even-handed assessment of a contractor’s
capabilities and resources, the bid of an incompetent may be rejected
and the action of the public agency upheld by the courts. It is
important to note, however, the courts have ruled against such
rejections when the proper procedures for rejection were not followed
including not doing the necessary homework of documentation and not
providing due process rights to the bidder by the granting of a hearing.
It must be clearly understood that the process of determining
responsibility is not a matter of comparing the low bidder’s
qualifications and background with those of other low bidders. The
notion that the second bidder is more qualified than the low bidder is
not sufficient reason for rejection of the low bidder. Each bidder must
be investigated individually and factually on a case-by-case basis. Once
the low bidder is determined not to be responsible, then may the
investigation begin on the next bidder.
While Section 103 of General Municipal Law contains no clear
definition of responsibility, case law and Section 120W of General
Municipal Law provide a good set of guidelines. They include:
- Adequate financial resources or the ability to obtain those
resources
- Ability to comply with the required or proposed delivery or
performance schedule
- Satisfactory record of performance
- The necessary production, construction and technical equipment and
facilities, or the ability to obtain them
- Eligibility to receive an award under applicable laws and
regulations (e.g., NYS Prevailing Wage Law)
- Past or present criminal or corrupt conduct
PREQUALIFICATION: Many
professionals are prone to seek prequalification of contractor, vendor,
manufacturer or subcontractor. In the private sector this is acceptable,
although caution should be taken to avoid undue limitations. In any
case, once pre-qualification has been exercised, post-qualification
should be avoided.
As to public work, the competitive bidding laws of New York State do
not permit prequalification or any other undue or arbitrary restriction
or barriers on entry into the marketplace. Such undue restrictions or
barriers include:
- Experience Prerequisites (…more)
- Restrictive Insurance or Bonding Requirements
- Mandatory Pre-Bid Meeting Attendance (…more)
- Sublisting (…more)
- Misuse of Qualification Statement Submitted with the Bid (…more)
Experience Prerequisites:
A lazy, albeit still illegal, method of prequalification has been to set
forth certain experience prerequisites. These experience requirements
have been viewed by the courts as arbitrary and anti-competitive (see Construction
Contractors Association and GBC v. the County of Orange). The
qualifications of any contractor should be looked at individually and
objectively. There is no empirical or other evidence to substantiate
that contractors meeting such experience requirements are necessarily
more qualified to do the work than ones falling short of those
requirements. More to the laws of New York State, there is no evidence
that one falling short of those requirements would necessarily be unable
to perform the work as specified.
Mandatory Pre-Bid
Meeting Attendance: Requirements for mandatory pre-bid meeting
attendance violate §103 of General Municipal Law in that they, too, are
forms of prequalification. They are also prone to dispute. What happens,
for example, if the low bidder did not attend the meeting? If you reject
him, he may bring an action; if you do not, the next lowest bidder
might.
What is the real purpose of the meeting? The competitive bidding laws
of New York State demand complete plans and specifications. If any
questions arise in the pre-bid meeting, it would be inappropriate to
answer verbally since only a written response in the form of an addendum
is enforceable.
If a consideration at all, pre-bid meeting attendance should only be
considered as one factor in determining the responsibility of the low
bidder and, even at that, only where there is some question whether the
bid was too low.
Qualification
Statements with the Bid: The low bidder only should be required
to submit qualification statements with related backup information
within a specified period of time, post bid. If, by objective evaluation
of the facts before you regarding that contractor, he is not responsible
then he should be rejected and the next bidder should be evaluated in
the same fashion. Requiring all bidders to submit this information with
the bid could lead one to the conclusion that you seek to compare
bidders.
Two practical problems with this requirement are: (a) it is an
unnecessary paperwork burden on all involved, and (b) by asking for this
information as part of the bid, you may not be able to shield
proprietary information from a Freedom of Information Request.
EQUIVALENTS – "OR EQUALS": As
a practical matter, owners do themselves a disservice when either by overt
or subtle specification competition is limited, particularly if
limited to one product or manufacturer. Such issues as bid
vs. list price and packaging can
have significant impact on price while, amazingly, impacts on project performance
might also be felt. On public work,
such restrictions are, for the most part, prohibited.
Overt and
Subtle Limitations of Competition: Proprietary specifications
come in two forms. The overt form is where one specific product is
specified and it is made clear to bidders that no equivalent products
will be accepted. The second, and more subtle, approach is to write a
performance spec which effectively precludes all but one product. While
neither form is good, this reviewer prefers the former. The latter is
sneaky!! It leads bidders down the primrose path, believing they have a
shot with another manufacturer. Only the supplier of the proprietarily
specified product knows the fix is in, and his price reflects it.
Contractors bid on alternatives looking to be competitive only to have
it blow up in their face. The contractor has been damaged and the
project has begun on the wrong foot.
Bid Price vs. List Price: It
must be recognized that many suppliers have at least two prices in their
repertoire, one for competitive situations and one for non-competitive.
In a competitive situation, the sharp-penciled "bid price" is
the one provided. In a non-competitive situation, the "list
price" is used. The list price can be considerably higher than the
bid price and, so long as the non-competitive message is in place, it is
unmovable. We have seen situations where suppliers, believing they had a
performance spec locked up due to long-time relations with the designer,
provided a price considerably higher than the competition. When this
reviewer and the contractor fought to break the barriers to competition
placed by the designer and won by going to the owner and the owner’s
attorney, the price from the supplier suddenly dropped 48%. Amazing!!!
Packaging: If a supplier of a number of
products has franchise control over a proprietarily specified product he
will not sell that product except in a package with a variety of other
products for which the owner or designer thought they had adequate
competition. Not only, then, will the proprietarily specified product be
at the "list price," the entire package will be at that
inflated cost. Calls to the manufacturer can sometimes break the package
but that is by no means a sure thing.
Performance Impacts: A second
disadvantage relates to the responsiveness of the supplier during
construction. We have found that as long as the supplier believes he has
the project sewn up and as long as there appear to be no later
repercussions, the proprietarily specified product can be difficult for
the contractor to manage. Indeed, the supplier no longer believes he
works for the contractor, in spite of a supply contract. He believes he
works directly for the owner or the designer. Often, the supplier
believes himself to be working for the users of the facility and not
even the construction and engineering side of the owner. This causes
numerous performance and responsiveness issues.
A good rule of thumb is to specify a minimum of three products (see
public work requirements below). This will generate enough competition
to alleviate the upward pressure on price. It is important that
designers thoroughly research those items listed. Too often, outdated
lists are used in which products listed are no longer made or the
manufacturer is out of business. In some circumstances, "Buy
American" provisions prohibit the use of two out of the three
products listed. We have even seen troubling situations where
contractors seek to use listed products only to have them rejected.
Public Work: Generally, the competitive
bidding statutes of New York State demand free and open competition
among equivalent products. First and foremost, that means the standard
in all public works specifications should be what is known as the
"or equal" clause. This clause essentially states that in the
technical specifications the words "or equal" or "or
approved equal" may be assumed after each and every list of
products. The fact is, the term "equal" is a misnomer. The
proper term is "equivalent." It is the performance of the
product that is important. The listed products set up a performance
standard, which must be met. It is not important that each bolt or
internal mechanism be exactly the same as the listed product, only that
it perform the same function to the same effectiveness.
Court cases have stated that either in interpretation of the
performance standards of the product or in the performance spec itself,
it is a violation of law to specify in such a way that only one product
may meet the spec. It has also been found that barriers placed in the
way of competition on said products are prohibited. In relation to this,
there are a number of more specific points to be explored. They are:
Pre-Bid Approval Requirements:
In 1972, the case of GBC v. the City of Syracuse was decided. In
relation to equivalents, that case found that any requirements which
demand that, in order to be considered an acceptable product,
application for acceptance must be made ten days prior to bid opening,
are extra legal. The court stated that such requirements amount to
illegal prequalification and a roadblock in the way of free and open
competition.
Equivalent Listing
Requirements: Similar to the prohibition of requirements for
pre-approval of equivalents is the prohibition of requirements that the
proposed equivalents and manufacturers be listed with the bid. For
guidance on this matter, the case of GBC v. the City of Syracuse
must again be consulted. It is found here that such requirements are an
illegal form of prequalification.
Payment for the
Privilege of Review: The idea that the contractor must pay the
designer for the privilege of reviewing the product for the equivalency
is equally offensive and is another roadblock in the way of free and
open competition.
The fact is, the designer was presumably paid to provide a set of
bidding documents that would facilitate the delivery of a quality
project on time and within budget. To accomplish that, one of the tasks
would be to maximize competition, as noted above. When it comes to
equivalent products, an owner should expect the design professional to
determine equivalency of a sufficient number of products to accomplish
that end, and to list them in the contract document. Recognizing that a
product might be missed by a design professional and wishing to
eliminate temptation to lock up specs due to laziness or graft, Section
103 of General Municipal Law has required that equivalents be freely and
openly encouraged.
The idea that the contractor is possibly being asked to pay for the
review discourages the use of equivalents. Moreover, this practice might
lead to a conclusion that the designer did not provide the service to
the owner and taxpayer that they contracted to provide. Instead, they
have limited competition, potentially increasing costs, and required the
contractor to pay for that which the owner has already paid. Of course,
those costs will eventually be paid by the owner anyway.
Bid Presumed
Based Upon Specified Products: Statements to the effect that the
contracts will be awarded "without consideration of possible
substitute or ‘or equal’ items" are violative of the provisions
of Section 103, General Municipal Law, which call for open competition,
thus requiring that the use of "or equals" be encouraged by
the public owner. The idea is that the owner achieves the benefits of
competition during the bidding. The low bid, therefore, must be based
upon the use of those equivalent products.
Post-Bid Price Change
on Equivalents: Clauses seeking to require the contractor to
credit the savings to the owner based upon the proposed equivalent
violates the very idea of an equivalent. The purpose is for the taxpayer
to gain the advantage of their use at bid time by the increased
competition. The price advantage will have already been granted in the
bid.
In addition, talk of price change on equivalent products may be
considered a form of negotiation also precluded by the competitive
bidding statutes.
Creation of
Competition Through Alternates: Noted recently is a misuse of
the alternate system in that attempts are made to create competition for
various products through the alternate bidding system. In effect, the
specifications call for the base bid to be based upon use of a
proprietary item with the ability to use other listed products by noting
a price change in the alternate lines.
Here again, §103 of General Municipal Law demands free and open
competition and it clearly prohibits specifications written in such a
way that only one manufacturer can meet the specs. Using the alternate
method does not meet the test of §103 in that you have simply set up a
series of proprietary specs and competition in the base bid has not been
created. In fact, to meet the test of §103, assuming the alternate
products are not equal to the base bid product, the bid should be based
on the base bid product "or equal." In addition, each
corresponding alternate should be on the listed product "or
equal." If, on the other hand, the alternate products are
equivalent to the base products, there should be no change in price on
any of the alternates. They will all be based on the same item.
Substitution vs. Equivalent:
Some confusion is often apparent in specifications as to the difference
between equivalents and substitutions. An equivalent is a product that
is equal to the standard of quality set in the documents. Its use should
be an option of the bidder so as to allow for a maximization of
competition. Inherently, the contractor takes a risk that his judgment
of the product equivalence is proper since the professional must approve
the equivalent, post bid. The price advantage has already been gained by
the owner in the bid by the maximization of competition.
A substitution, on the other hand, is a product of lesser or greater
quality which does not meet the performance requirements of the specs.
It is not inappropriate in that case to request price changes.
Performance
Specifications Plus Manufacturer List: Much confusion erupts
when specifications include both a detailed performance specification
and a listing of acceptable products. As to the former, contractors must
supply a product that meets the performance specification. As to the
latter, the contractor must supply a product listed "or
equal."
The confusion occurs where (1) the time requirements for submitting
proposed equivalents are not met and the designer seeks automatic
rejection. In point of fact, given the performance spec, the "or
equal" provisions don’t really apply. (2) One or more of the
listed products don’t meet the performance specification.
The Mythical Rule of Three:
In our travels we have often heard from both contractors and designers a
myth about "or equal" requirements. That myth surrounds the
rule of thumb that a minimum of three manufacturers be listed in the
specifications. Contractors believe that it is a violation of law if at
least three are not specified. While this reviewer understands that some
municipalities have internal guidelines to this effect, there is no such
requirement tied to the State competitive bidding statutes. Designers,
on the hand, believe that if the "minimum" of three is listed,
they do not have to accept equivalents. That, too, is untrue. If ten are
listed, the "or equal" clause must still be used. As noted
above, three might be listed but, for a variety of reasons (i.e., buy
America provisions, discontinued manufacture), only one of the products
may, in reality, be used.