|
Liquidated
Damages/ Bonuses
Liquidated damage clauses have a number
of drawbacks that owners should consider. First and foremost should be
the question of competition. Contractors may shy away from projects with
an inordinate amount of risk in this regard. In some cases, the
contractor may have little choice; their bonding company may say no.
In addition, in a low, lump sum bidding
format, you run the risk of attracting those who believe they can escape
and evade the liquidated damage charges. That evasion will take the form
of counterclaims, delay damage claims, and the burying of everyone in
paperwork. Even those not otherwise inclined to that mode of operation
are forced into it by such clauses, particularly in a poor economy.
Multiple contracts are often viewed as facilitating the ability to
escape and evade.
A subject that often comes up in the
context of liquidated damages is a bonus clause. In a practical sense,
we are not certain that there is much difference between the two except
for semantics. Contractors often bid in anticipation of being paid the
bonus. If they lose the bonus, they lose money. In effect, loss of bonus
is a liquidated damage penalty. Given that, the same aggravations occur.
Liquidated damage or, for that matter,
any consequential damage threats create a situation that is the
antithesis of partnering. A contractor is forced into over-documentation
and expensive claims building. The relationship is adversarial right out
of the box. As we said to one owner recently, "You seem to be
spoiling for a fight rather than looking for ways to work with the
contractors as a team to complete the job on time, within budget, and
with a minimum of dispute."
Should you opt for liquidated damages,
the following basic ground rules apply:
- Liquidated damages are enforceable
only if, in fact, the owner was actually damaged, and they are not
to be used for punitive purposes. If the delay in completion would
have occurred anyway or if the owner would not have been able to
occupy at the completion date, the damages are not generally
considered enforceable.
- The damages must bear some resemblance
to what actual damages might be.
- You must be able to attribute the
lateness to the contractor you intend to charge liquidated damages.
- You may charge liquidated or actual
damages, but not both (see 36 NY Jur 2d, Damages, §170 and cases
cited therein, wherein it is found that where a liquidated damage
sum is stipulated, that amount is the maximum amount which may be
recovered).
Public Work Considerations:
When you are dealing with separate prime contractors, as is required on
public work under the Wicks Law, the issue is even more difficult. Who
was at fault for the delay? If the electrical contractor does not finish
timely, he might contend that the plumbing contractor delayed him or
that the owner was not really damaged because the general construction
contractor was not scheduled to complete the project by that time
anyway. All contractors might contend that the delay was caused by the
owner’s abdication of his responsibility to coordinate the separate
primes.
In relation to separate prime
contractors, we often see clauses that seek to charge general
construction contractors $1,000/day liquidated damages while charging
the other primes only $300/day. This brings into question what the
actual damages were, $1,000 or $300? The size or type of contract should
not be a determining factor in the amount. Either the project is
completed and suitable for occupancy or it isn’t. A choice must be
made to either raise the amounts of the other primes or reduce that of
the general construction contractor or get rid of the clause altogether.
We would suggest looking at those options in reverse order of
preference.
|