1. HEAT DURING CONSTRUCTION
1.1 PHASE I – BUILDING NOT ENCLOSED
1.1.1 Prior to the time the building is enclosed, heat shall be
provided by each Prime contractor, as required to accomplish the
following:
1.1.1.1 Protect his completed work;
1.1.1.2 Protect material and equipment being installed;
1.1.1.3 Enable his workmen to accomplish their work in a satisfactory
manner; and
1.1.1.4 Maintain the approved progress schedule.
1.1.2 The building shall be considered enclosed when the exterior
surfaces are completed sufficiently to exclude the elements and retain
heat. The General Construction Contractor shall make all permanent or,
at his option, temporary enclosures of the exterior surfaces of the
building to exclude the elements and retain heat as soon as practical in
accordance with the approved progress schedule. It shall be the
responsibility of the General Construction Contractor to notify the
Architect and the other Prime Contractors that the building is enclosed.
1.2 PHASE II – BUILDING ENCLOSED – PERMANENT HEATING SYSTEM
NOT READY FOR OPERATION
1.2.1 When the building is enclosed as defined in 1.1.2, heat shall
be provided as hereinafter defined in 1.2 PHASE II, and as required to
accomplish the following:
1.2.1.1 Protect completed work;
1.2.1.2 Protect material and equipment being installed;
1.2.1.3 Enable workmen to accomplish their work in a satisfactory
manner; and
1.2.1.4 Maintain the approved progress schedule.
1.2.2 Within (e.g. 30) calendar days of notification of enclosure the
General Construction Contractor, Plumbing Contractor and Electrical
Contractor shall have sufficiently completed all work including required
tests for which he is responsible to enable the Heating and Ventilating
Contractor to sufficiently complete the permanent heating system and
related controls and safety devices to enable the owner to accept and
commence operations of the system.
1.2.3 Within (e.g. 60) calendar days of notification of enclosure the
Heating and Ventilating Contractor shall have the permanent system and
related controls and safety devices sufficiently completed, including
required tests, to enable the owner to accept and commence operation of
the system. The following items are not required to be complete:
1.2.3.1 Equipment and material required solely for the purpose of
exhaust ventilation and in no way connected to related to the
generation and distribution of heat, except as may be required for the
proper operation of the components of the heating system being
accepted.
1.2.3.2 Miscellaneous grilles, louvers, and covers.
1.2.3.3 Individual room temperature control which is in no way related
to or connected to generation equipment temperature control; but,
temperature control in areas other than the generation equipment shall
be provided, and may be temporary in nature to control each basic area
of the building as an individual zone.
1.2.3.4 Minor and miscellaneous insulation outside the Boiler Room.
1.2.4 It shall be the responsibility of the Heating and Ventilating
Contractor to notify the Architect and the other Prime Contractors that
the heating system is complete as required in 1.2.3.
1.2.5 The General Construction Contractor shall provide heat until
the permanent heating system is operable as required in 1.3. PHASE III.
All cost including but not limited to fuel and/or energy cost, for heat
provided by the General Construction Contractor shall be paid for by the
General Construction Contractor except as provided in 1.2.6.
1.2.6 Any Prime Contractor who fails to progress his work as required
in 1.2.2 and 1.2.3, and who thereby delays the completion of the work as
required in 1.2. PHASE II, shall pay all cost of continuing heat as
required under 1.2 PHASE II. Should two or more Prime Contractors fail
to progress their work as required in 1.22.2 and 1.2.3 they shall
jointly be held liable to pay all cost of continuing heat as required
under 1.2. PHASE II.
1.2.7 The method of heat shall meet all applicable codes and
ordinances. Heat provided by the General Construction Contractor under
1.2 PHASE II shall be maintained at not less than 50 degrees F. unless
lower temperatures are sufficient to meet the requirements of 1.2.1.
1.3 PHASE III – BUILDING ENCLOSED – PERMANENT HEATING SYSTEM
OPERABLE
1.3.1 When those portions of the General Construction, Plumbing,
Electrical and Heating and Ventilating work are complete as defined in
1.2.2 and 1.2.3, the owner shall accept those portions of the work
including related controls and safety devices and use, operate and
maintain them to provide heat.
1.3.2 By accepting the permanent heating system and related controls
and safety devices, the Owner agrees to:
1.3.2.1 Begin the guarantee period for the work completed and
accepted as of the date of acceptance;
1.3.2.2 Assume full responsibility for the proper operation and
maintenance of all accepted portions of the heating system;
1.3.2.3 Provide sufficient heat continuously to (1) protect completed
work, (2) protect material and equipment being installed, (3) enable
workmen to accomplish their work in a satisfactory manner, and (4)
maintain the approved progress schedule;
1.3.2.4 Pay all cost including fuel and/or energy cost for the
operation and maintenance of the heating system.
1.3.3 Failure of any Prime Contractor to guard against unnecessary
heat loss during 1.3 PHASE III shall render him liable for the resultant
fuel cost.
1.3.4 Acceptance of the permanent system relates only to
responsibility for damage caused by the owner’s neglect and normal
wear and tear. No Prime Contractor is relieved of any contractual
requirement for furnishing a complete and operating system in perfect
condition at the completion of the work.